No. R-III/25/PNOP/2018                              Dated  06-08-2018
To
Member (O), 
Department of Posts,
Dak Bhawan,
New Delhi-110 001.
Subject:- Postponing the implementation date of
PNOP.
Respected sir,
                     Kindly refer to the  meeting held 
on 28-05-2018 on PNOP and calling suggestions on PNOP. Staff Side R-III
CHQ has submitted the suggestions vide its letter of even number dated 27-06-2018  (Copy enclosed). Now it is learnt that Department
has issued orders to implement the PNOP w.e.f. 17-08-2018. In this regard we
submit the following for consideration:_ 
1.   It is very sorry to
inform that not a single suggestion given by the Staff Side has been  accepted by the Department and also the Administration
has also not  clarified all  the points/anxiety raised by the Staff Side.
2.   No discussion was
held at Circle /Regional level for selection of L-1, L-2 hubs and mail
arrangements. Due to unscietific selection of hubs without considering
geographical situations, large scale back routing and accummulation in L-1 hubs
will be resulted.
3.   Sufficient space and
other infrastructure facilities has not been provided in earmarked parcel hubs.
4.   The problem  due to the CSI role out is not settled,  in addition to that implementation PNOP
without providing the minimum requirements will create more difficulties to the
staff and lead to public criticism.
                  Therefore due to above
reasons we would request you to kindly postpone the implementation of PNOP from
17-08-2018.
With regards.
Yours
sincerely,